CMW has completed the expansion of the Steritech Merrifield plant.

Experiencing massive growth in the requirement for their services during the pandemic, Steritech launched their Merrifield expansion.

The Merrifield plant is Steritech’s newest facility completed by CMW in 2019, with the extension adding an additional wing to each side of the existing warehouse totalling approximately 1,300m².  The new extension makes provision for further improvements in the future including the upgrade to temperature-controlled zones.  The works also included changes to the existing layout of Steritech’s offices.

CMW was able to deliver the additional warehouse area with minimum disruption to the plant operation that ran at full capacity throughout the construction period.  The work was completed on program, providing vital storage space as Steritech approach their peak period at the end of the summer harvest.